June Update



It's been a dynamic period on-site, witnessing significant progress across all our stages. If you've driven by lately, you'll see the impressive shape the building is taking. We're thrilled to bring you the latest updates.

 

First and foremost, we're delighted to announce that Global Business Park is now completely sold out across all stages. We extend our heartfelt gratitude to our buyers who've become part of our community since our last newsletter. For those still interested in joining us, kindly reach out to Rob Luca or Daniel Makin, who will gladly add you to our waitlist for any potential future availability.


STAGE TWO PROGRESS

To our Stage 2 buyers, we're excited to share that we're nearing practical completion. By the end of July, we anticipate reaching this milestone, followed by the issuance of certificates of occupancy and titles.

 

Please note that we are unable to give timeframes for certificate of occupancy and titles as these are given by City of Wanneroo and WAPC respectively.  Rest assured, we're in close coordination with both entities to ensure a seamless application process.

 

Your sales agent will keep you informed of progress. Settlement will occur 14 days after titles are issued, so please ensure you've nominated a settlement agent and shared the details with your sales agent if you haven't already done so.


STAGE THREE PROGRESS

For our Stage 3 buyers, we're pleased to provide the following progress report:

  • Suspended slabs have been completed and roof works have also been completed.

  • Painting has commenced and will continue throughout the remainder of Stage 3.

  • Architectural framework has commenced with timber feature cladding to be installed in the coming weeks.

  • Internal works are well underway.

 

We anticipate practical completion for stage 3 in September/October 2024.



We take this opportunity to express our gratitude to all our buyers for your patience during the challenges faced in the Perth building industry, which has led to some delays.  Our subcontractors are working tirelessly to complete their works despite the labour shortages that they are all facing. 


Our commitment to delivering a building worthy of our Design Matters National New Commercial Build over $2M award has remained unwavering. We appreciate your understanding as we strive to complete the project to the highest standards within a reasonable timeframe.

 

We eagerly anticipate welcoming you to Global Business Park soon.